Breaker-to-Breaker Registry

A breaker-to-breaker run is one refueling outage to the next with no unplanned shutdown in between. It is the cleanest single read on whether a reactor is well run.
Filtered to Duke Progress CAISO TVA MISO Show all markets
Who is running clean, and for how long Individual · $165/mo

Continuous days on line for every reactor, which ones are inside a qualifying breaker-to-breaker run right now, how many they have completed, and how long since each one last tripped.

  • Current streak for all 94 units
  • Qualifying runs and champions
  • Days since the last reactor trip
  • Completed run history per unit

Current Runs · Duke Progress + 3 more

alphabetical · 26 units
#UnitMarketMW Streak and trip record Individual
· Arkansas Nuclear 1 MISO 826 █████
· Arkansas Nuclear 2 MISO 982 █████
· Browns Ferry 1 TVA 1,227 █████
· Browns Ferry 2 TVA 1,208 █████
· Browns Ferry 3 TVA 1,227 █████
· Brunswick 1 Duke Progress 938 █████
· Brunswick 2 Duke Progress 932 █████
· Callaway MISO 1,190 █████
· Clinton MISO 1,079 █████
· Diablo Canyon 1 CAISO 1,122 █████
· Diablo Canyon 2 CAISO 1,118 █████
· Fermi 2 MISO 1,141 █████
· Grand Gulf 1 MISO 1,397 █████
· Harris 1 Duke Progress 964 █████
· Monticello MISO 617 █████
· Point Beach 1 MISO 589 █████
· Point Beach 2 MISO 597 █████
· Prairie Island 1 MISO 521 █████
· Prairie Island 2 MISO 519 █████
· River Bend 1 MISO 968 █████
· Robinson 2 Duke Progress 759 █████
· Sequoyah 1 TVA 1,148 █████
· Sequoyah 2 TVA 1,126 █████
· Waterford 3 MISO 1,087 █████
· Watts Bar 1 TVA 1,123 █████
· Watts Bar 2 TVA 1,122 █████
Toward B2B is progress through a full fuel cycle: a run only qualifies once the unit has gone from one refueling outage to the next without an unplanned shutdown, so the threshold is set per unit rather than as one fleet-wide number. Days since trip spans refuelings and is the longer-horizon read.
A long streak is not the same as a firm date Pro · $499/mo

A unit can run clean for six hundred days and still hand back an outage two weeks late. The overrun projection is the number that says which.

  • Projected overrun days per unit
  • Scored against its own outage history
  • MW-days the market has not priced