NukeGryd
Market Briefing · updated daily

Markets

Where U.S. nuclear supply is tightest right now, and what is coming off line next. As of Sep 15, 2026 · Updated every morning from the NRC Daily Power Reactor Status Report.
Most-stressed Market
PJM
5.9% offline · 1,939 MW
MW in Refueling Now
1,837 MW
2 units at a full outage
MW at Risk · Next 60 Days
megawatts due off line within 60 days
Biggest 30-day Mover
PJM
availability ▼ 4.7 pts

By Market

Available nuclear MW now, the day's move, vs 7-day and a year ago, and the 30-day trend, by balancing authority
ISO / RTO 31u
PJM
30,752 MW
94.1% available ↗ 263 MW DoD
vs 7d avg+560 MW (+1.9%)
vs 1 yr ago██
Fleet record ██ ██
Fall 26 avg offline 492 MW
What to watch Active: North Anna 2 · −943 MW since Aug 19, 2026
Vertically Integrated 4u
3,593 MW
100.0% available 0 MW DoD
vs 7d avg+40 MW (+1.1%)
vs 1 yr ago██
Fleet record ██ ██
Fall 26 avg offline 16 MW
What to watch All units at full power
ISO / RTO 2u
2,240 MW
100.0% available ↗ 78 MW DoD
vs 7d avg+166 MW (+8.0%)
vs 1 yr ago██
Fleet record ██ ██
Fall 26 avg offline 15 MW
What to watch All units at full power
Available MW = nuclear generating MW now (installed nuclear MW minus what is offline), at the 98% full-power floor. DoD is the change since yesterday; the 30-day spark is the market's availability (% of its nuclear fleet generating). "What to watch" is the largest unit offline now, with the date it went down.

Biggest 30-Day Movers

Signed change in nuclear availability over the last 30 days
PJM
↘ −4.7 pp
Duke Progress
↗ +0.0 pp
CAISO
↗ +0.0 pp
Change in each market's nuclear availability (generating MW as a share of installed nuclear MW) between 30 days ago and today. Positive points = more nuclear back online.

Most-stressed Markets

By share of nuclear fleet offline, lowest availability first
MarketTypeUnits Availability MW Offline % Offline Grid tomorrow 30d Δavail
PJM ISO/RTO 31 94.0% 1,939 5.9% soft ▼ 4.7
Duke Progress Non-ISO 4 100.0% 0.0% ▲ 0.0
CAISO ISO/RTO 2 100.0% 0.0% soft ▲ 0.0
Availability = nuclear generating MW ÷ installed nuclear MW. "Grid tomorrow" is the day-ahead demand forecast vs the trailing-30-day norm, where a nuclear loss bites hardest. 30d Δavail is the change in the market's nuclear availability over the last 30 days.

Which market is about to be short, and by how much

Which units come off line next, when, and how much capacity is at risk by market (our sourced dates plus model projections) is part of NukeGryd Individual and up. Today's live market stress stays free.

See plans

Ontario (IESO) separate fleet

Ontario detail
MW Offline
3,632 MW
29.9% of the Ontario fleet
Units Offline
4 of 16
Bruce, Darlington, Pickering
Delivering
8,528 MW
of 12,160 MW installed
Resolution
1 hour
vs. once-daily for the U.S. fleet

Ontario supply, for the northeast picture. Ontario is reported as a separate fleet and is never added into the U.S. national figures above. IESO grid-operator market data (MW delivered), not NRC percent-power.