NukeGryd
Fleet by NRC Region · updated daily

Regions

The U.S. nuclear fleet across the NRC's four regulatory regions. As of Sep 15, 2026 · Updated every morning from the NRC Daily Power Reactor Status Report.
Online Now
15,888 MW
92.0% of 17,270 MW installed
Fleet Availability
92.0%
nuclear generating ÷ installed
Units in Outage
1
at a full outage (0% power)
Units Derated
3
running below 98% power
Region II

Southeast

Atlanta, GA
91.7%
availability
14,056 MW
online of 15,322
1,266 MW
offline
16 units: 13 at power 2 derated 1 in outage
Top markets
Southern 8,080 MW FPL 3,649 MW Duke Progress 3,593 MW
Region IV

West / South-Central

Arlington, TX
94.1%
availability
1,832 MW
online of 1,948
116 MW
offline
2 units: 1 at power 1 derated
Top markets
SPP 1,948 MW

Region Summary

RegionCoverageUnitsCapacity OnlineAvailability MW OfflineOffline / DeratedTop markets
Region II Southeast 16 15,322 14,056 91.7% 1,266 1 / 2 SouthernFPLDuke Progress
Region IV West / South-Central 2 1,948 1,832 94.1% 116 0 / 1 SPP
NRC regions are administrative areas of the U.S. Nuclear Regulatory Commission, derived here from each plant's state. Availability = generating MW ÷ installed MW.

Fleet by Region

Every reporting unit, grouped by region, biggest supply loss first
UnitMarketStatePowerCapacityMW offlineStatus
Region II · Southeast (16 units, 14,056 MW online)
Vogtle 2 Southern GA 0.0% 1,152 1,152 Outage
Saint Lucie 2 FPL FL 92.0% 987 79 Derated
Hatch 2 Southern GA 96.0% 883 35 Derated
Vogtle 1 Southern GA 100.0% 1,150 At power
Vogtle 3 Southern GA 100.0% 1,114 At power
Vogtle 4 Southern GA 100.0% 1,114 At power
Saint Lucie 1 FPL FL 100.0% 981 At power
Harris 1 Duke Progress NC 100.0% 964 At power
Brunswick 1 Duke Progress NC 100.0% 938 At power
Brunswick 2 Duke Progress NC 100.0% 932 At power
Farley 2 Southern AL 100.0% 896 At power
Farley 1 Southern AL 100.0% 895 At power
Hatch 1 Southern GA 100.0% 876 At power
Turkey Point 4 FPL FL 100.0% 844 At power
Turkey Point 3 FPL FL 100.0% 837 At power
Robinson 2 Duke Progress SC 100.0% 759 At power
Region IV · West / South-Central (2 units, 1,832 MW online)
Cooper SPP NE 85.0% 772 116 Derated
Wolf Creek 1 SPP KS 100.0% 1,177 At power

Ontario (IESO) separate fleet

Ontario detail
MW Offline
3,632 MW
29.9% of the Ontario fleet
Units Offline
4 of 16
Bruce, Darlington, Pickering
Delivering
8,528 MW
of 12,160 MW installed
Resolution
1 hour
vs. once-daily for the U.S. fleet

Ontario is not an NRC region, so it sits outside the table above. Ontario is reported as a separate fleet and is never added into the U.S. national figures above. IESO grid-operator market data (MW delivered), not NRC percent-power.