NukeGryd
Fleet by NRC Region · updated daily

Regions

The U.S. nuclear fleet across the NRC's four regulatory regions. As of Sep 16, 2026 · Updated every morning from the NRC Daily Power Reactor Status Report.
Online Now
17,223 MW
85.3% of 20,198 MW installed
Fleet Availability
85.3%
nuclear generating ÷ installed
Units in Outage
2
at a full outage (0% power)
Units Derated
2
running below 98% power
Region II

Southeast

Atlanta, GA
81.7%
availability
13,286 MW
online of 16,261
2,975 MW
offline
15 units: 11 at power 2 derated 2 in outage
Top markets
TVA 8,181 MW Southern 8,080 MW
Region IV

West / South-Central

Arlington, TX
100.0%
availability
3,937 MW
online of 3,937
0 MW
offline
3 units: 3 at power
Top markets
SRP 3,937 MW

Region Summary

RegionCoverageUnitsCapacity OnlineAvailability MW OfflineOffline / DeratedTop markets
Region II Southeast 15 16,261 13,286 81.7% 2,975 2 / 2 TVASouthern
Region IV West / South-Central 3 3,937 3,937 100.0% 0 / 0 SRP
NRC regions are administrative areas of the U.S. Nuclear Regulatory Commission, derived here from each plant's state. Availability = generating MW ÷ installed MW.

Fleet by Region

Every reporting unit, grouped by region, biggest supply loss first
UnitMarketStatePowerCapacityMW offlineStatus
Region II · Southeast (15 units, 13,286 MW online)
Browns Ferry 1 TVA AL 0.0% 1,227 1,227 Outage
Vogtle 2 Southern GA 0.0% 1,152 1,152 Outage
Vogtle 3 Southern GA 60.0% 1,114 446 Derated
Hatch 2 Southern GA 83.0% 883 150 Derated
Browns Ferry 3 TVA AL 100.0% 1,227 At power
Browns Ferry 2 TVA AL 100.0% 1,208 At power
Vogtle 1 Southern GA 100.0% 1,150 At power
Sequoyah 1 TVA TN 100.0% 1,148 At power
Sequoyah 2 TVA TN 100.0% 1,126 At power
Watts Bar 1 TVA TN 100.0% 1,123 At power
Watts Bar 2 TVA TN 100.0% 1,122 At power
Vogtle 4 Southern GA 100.0% 1,114 At power
Farley 2 Southern AL 100.0% 896 At power
Farley 1 Southern AL 100.0% 895 At power
Hatch 1 Southern GA 100.0% 876 At power
Region IV · West / South-Central (3 units, 3,937 MW online)
Palo Verde 2 SRP AZ 100.0% 1,314 At power
Palo Verde 3 SRP AZ 100.0% 1,312 At power
Palo Verde 1 SRP AZ 100.0% 1,311 At power

Ontario (IESO) separate fleet

Ontario detail
MW Offline
3,640 MW
29.9% of the Ontario fleet
Units Offline
4 of 16
Bruce, Darlington, Pickering
Delivering
8,520 MW
of 12,160 MW installed
Resolution
1 hour
vs. once-daily for the U.S. fleet

Ontario is not an NRC region, so it sits outside the table above. Ontario is reported as a separate fleet and is never added into the U.S. national figures above. IESO grid-operator market data (MW delivered), not NRC percent-power.